WE Report

Lessons Learned

Lesson Learned





By: Lars Solvang

Report No.

2199

Discipline/Origin

Bleed of package
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/10/04
1525 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Equipment
Negative

Borgland Dolphin


What happened in P&A:
Hydrocarbons contamination required a bleed off package to be installed.

What Was Planned

Circulate out annulus content between 9-5/8″ and 13-3/8″ plus 13-3/8″ and 20″ casing to mud pits.

What Was Learned

A bleed of package is required.